Scheduled a load to an ODS. The request has turned red. It has already loaded about 3 million records.

In the 'Details' section of the Monitor, the TRANSFER(IDOCS TRFC) , 3 data packages, say 1, 2, 3 are red. The same data packets1, 2, 3 are green under PROCESSING(DATA PACKET) tab. The job is till running when checked in SM37 though nothing is happening for about 12 hours now. RFC is in place.#

Any suggestions on what to do?

Thanks in advance.

Monica

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

check the processing tab. In case the number of records of that datapackages is somehow realistic and comparable with the others it will be fine. Then check if the process is really still running. Also check the source system for that. In case it has finished and no more data packages arrive, set the status to green and activate the request in the ods manually.

regards

Siggi

Former Member
0 Kudos

Hi

Change the max wait time and decrease the data packet size on Ipack-scheduller then reschedule the load.