on 09-03-2008 11:53 AM
Dear SAPIENTS,
I have done goods reciept of material and inspection lot generated, RR/UD done and material is accepted and than posted material in unrestricted stock. But I found that material is not ok. Now I wan to reject that material to vendor.
Can anybody explain me how to do this?
Regards,
Kaushal Rai
Hi,
The Process of creation of Return Purchase Order is as same an creation of Normal Purchase order except for activation of u201CReturns itemu201D indicator at the item level.
Enter the Batch No. of materials that are managed in batches. The Gross Price along with any other charges need to entered in the condition tab. Save the Purchase order.
Once the Purchase Order is released the Stores Dept. can be informed to do the Goods receipt for the PO
Goods Receipt for Return PO
By doing the GR with movement type 101 against a Return Purchase Order the system internally assigns movement 161. Please specify the storage location and Stock type for the material and batch number if not mentioned in the PO. Please enter the Delivery note reference in the appropriate tab and post the document.
As the GR is posted you will find that the stock has been reduced from the system henceforth do the Invoice Verification for the Purchase Order.
Invoice Verification
Do the Invoice Verification using MIRO with transaction as credit memo
Subsequent to Invoice Verification the Vendor account gets debited with the appropriate cost.
Regards
Merwyn
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In case the Invoice Verification/ Payment is complete and you are unable to use 122 movement for returning,
You can create a return PO for the item and then do a GR (movement type 161) and then raise a credit memo, refering to the Return PO
Regards
Merwyn
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
can use any of the below...
1.you can scrap the material from unrestricted use only from the tcode MIGO...
2. Cancel the doc..
3. reverse the doc...
4. POst it to blocked stock...if in case req.
PLs choose the correct mvt type....
Hope it helps....
Regards
Priyanka.P
AWARD IF HELPFULL
Edited by: Priyanka Paltanwale on Sep 3, 2008 12:57 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
You can just return the material to vendor using MIGO-RETURN DELIVERY reference using movement type 122.
Regards,
Syed Hussain.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.