With what value finish product as come when we do goods recipt from prd

former_member311909
Participant
0 Kudos

Hi,

With what value finish product as come when we do goods recipt for oa prodution order in make to order scenerio.

The material is not talking standard price form th e material master when we are doing goods recipt.

Regards,

somiraghu

Accepted Solutions (1)

Accepted Solutions (1)

pankaj_singh9
Active Contributor
0 Kudos

Hi,

Generally, Sales Order Stocks are valuated separately not as per the Standard Price or MAP of the Material Master. So, it will take value of the components issued and Operation Cost (from Activity types)

Answers (2)

Answers (2)

former_member311909
Participant
0 Kudos

As per costing varient.The value of material is updated.

Former Member
0 Kudos

If you use non-valuated sales order stock (account assignment E) there will ne no value posting at all during GR, thus also no accounting document. The full actual costs (that Pankaj listed) will be posted during settlement of the production order.