Costin Process order

we recently changed one of the BOM componet's std cost using manual price update , Later when we create new Process order for the main material, The target costs are at current standrd cost and the Actual costs are at the previous cost estimate for the BOM material and giving Variance, Please let me kow what is making BOM material to show cost at previous cost estimate in Actual cost column in Process order,

your help greately Appreciated,

Paarthu