on 09-02-2008 10:21 PM
Hi,
We have configured the Replenishment TO During TO Confirmation it works, however it does not take into account the replenishment qty defined in the material master, instead, it just takes the quantity of the first storage bin that it finds with the same material... Can anybody help us, what's missing????
Thx.
Edited by: Mariana Hernandez on Sep 2, 2008 11:22 PM
This is what I got as response...
I've reviewed the above description and would like to provide you the
following information :
...
What you are experiencing is the standard behaviour with reference to
the replenishment procedure.
The replenishment report creates transfer requirements, regardless of
the present availability of the material and in equal amounts to the
replenishment quantity set in the material master, or a multiple of
this. The replenishment quantity is limited by the maximum allowed
quantity in the storage bin.
You can set an indicator in transfer requirements for automatic TO
creation using RLAUTA10.
For RLAUTA10, you can also allow partial creation which is a possible
solution for the issue you described.
...
Hope this helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Any help
Edited by: Mariana Hernandez on Sep 4, 2008 5:39 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.