hi

can any body told me what is t.code of price change in purchase order

and schedule agreement

rks

Accepted Solutions (0)

Answers (10)

Answers (10)

Former Member
0 Kudos

hi,

Use Following Tcode:

ME22N - To Change price in purchase order

ME32L - To Change Scheduling Agreement.

MR21-To change moving average price

Regards

Manish Joshi

former_member581212
Active Contributor
0 Kudos

Hi,

You can change you price in ME22N - For change Po Document

You can Change Sch. agreement doc - ME31L - For change Sch. ag. doc...

Always remember...the serials mostly in sequence ...for eg :

me21n - Create po

me22n - for change PO

me23n - for display PO...

Hope it helps...

Regards

Priyanka.P

AWARD IF HELPFULL

former_member192897
Active Contributor
0 Kudos

For Purchase Order Price Change use ME22N

For SA Price Change Use ME32L

For Material Master Moving Average Price / Standard Price Change Use MR21.

Regards,

Ashok

srinivasa_maruvada
Active Contributor
0 Kudos

Hi

Goto ME22N for PO change

Goto ME32K for SA change

Goto MR21 for change of material price

Cheers

Srinivas

pankaj_singh9
Active Contributor
0 Kudos

Hi,

Price of Purchase Order and Scheduling Agreement can be changed in change mode of the the documents.

ME22N - Change Purchase Order

ME32L - Change Scheduling Agreement

Former Member
0 Kudos

Hi

In material master if u want to change u can goto mr21. and in po u can change in me22n. for sch me35l

regards

ram

Former Member
0 Kudos

Hi,

For PO T.code ME22N and for SA ME33l.

Regards,

Satya

former_member335885
Active Contributor
0 Kudos

HI,

ME22N - Change of Price for PO

ME35L - Change of Price for SA

TO change material master price MR21

Thanks

Kiran

Former Member
0 Kudos

hi

you can change price in Po by going to me22n and for schedule agreement is me32L

to change MAP tcode is MR21.

Regards,

Vijay

Former Member
0 Kudos

If any Transaction is not done against purchase order.

Then try ME22N - for purchase order,

and also check ME32L - Change Scheduling Agreement.

Regards,

Mahesh Wagh.