0Material_ATTR - Last delta update is not yet completed

Former Member
0 Kudos

Hi Gurus

I am getting the following error when performing a delta extract of 0Material_attributes

Last delta update is not yet completed

Therefore, no new delta update is possible.

You can start the request again

if the last delta request is red or green in the monitor (QM activity)

However it doesnt give me the request id or any other info.

The last request in the manage screen is green

Any ideas

HKF

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Check for previous delta run logs and check if any delta load has not yet completed. If you happen to find some previous delta run still running try to fix it else force the QM monitor to red and try performing a repeat delta.

Hope it helps !

Regards,

Rose.

Former Member
0 Kudos

Hi Rose

Thanx for your reply.

Do I look in RSMO for yellow delta logs or is there a better way?

HKF

Former Member
0 Kudos

Hi,

If you are process chains, in the log view you can see. You can also go to infopackage, click on the monitor button it shall ask for data range for which the log has to be displayed give it you can see the log.

Hope it helps !

Regards,

Rose.