Hi Experts,

I am doing the exercise of project I/00## in CA830.

I have planned the costs using Easy Cost Planning.

While I allocate the budget, the planned costs can not be copied to the 'Planned Total' view in CJ30.

May somebody guide me how to solve this problem.

Thanks in advance!

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi;

1. First of all you go to CJ30.

2. Select the relevant WBS or if u wana get all Planned values of every WBS.

3. Select from Period (Over all / Year).

4. Now at the Top Menu Choose Settings > Planned Total Version.

5. A small popup will display, input your planning Version, and hit OK.

Now repeat (3) ,same for yearly Budget if u have chosen previously overall.

I hope this solves ur problem.

former_member214674
Contributor
0 Kudos

Hi,

Check the year in which you have planned. or if it is overall.

Regards

Former Member
0 Kudos

Dear Abhinay,

Thank you very much, your advice does work.

Further, I want to know how to display the Planned costs with the 'Overall' mode. In the budget profile, both the indicators of 'Total values' and 'Annual values' have been set.

Former Member
0 Kudos

Check have you selected the same version for which you have done your planning via CJ30 - Settings - Planned total version.

Arya

Former Member
0 Kudos

Dear Arya,

Thank you very much, I will try it later.

Former Member
0 Kudos

Hi Allen,

Select the WBS & Click on Annual Overview.

Regards'

Syed

Former Member
0 Kudos

Dear Syed,

Thank you very much, and your advice does work.

Further, I want to know how to display the Planned costs with the 'Overall' mode. In the budget profile, both the indicators of 'Total values' and 'Annual values' have been set.