on 09-02-2008 10:26 AM
Hi,
Could you please tell me where can I find following dates & time in customizing.
1) Transit time & transit date
2) Loading time & loading date
3) Pick/Pack time
4) Transportation Lead time
Also can you give one example of forward scheduling & backward scheduling.
Thanks
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
U can maintain all this in
Spro-Img- S&D - Basic functiontion- Routes- Maintain Routes & Stages- Route.(0VTC)
Here u can Maintain
1. Transit Time (In Days)
2.Travel & Duration.
U can reschedule All this in Delivery Header.by pressing Schedulling Tab Page in delivery Header.
Revert if not resolved
Regards
Amit Gupta
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi..
when u r creating sales order first system will go with backward scheduling if it is not reach the dates then system will go for forward scheduling.
Backward Scheduling:
material available datepick/pack time loading time transit timetransportation lead time
for ex order dated is 1st req deliver date is 10th assume like this
for pick/pack time = 2
for loading time = 2
for transportation lead time = 2
for transit =5
in backward scheduling from 10th
522+2 = 11days it is taking that means it crossing the order date ate the time it will go for forward scheduling
from 1st on wards 222+5 it will confirm 11th..
this is happening when the material is available on 1st.
If the material is not available then it will find material available date suppose that is on 3rd the sysstem will calculate like this 225 = 9 ( forward scheduling ) it will not consider Transportation lead time i.e( Lorry arrangement time ) because we can do this arrange ment between 1st and 3rd. then sys confirm on 3rd + 9days i.e 12th.
Pick/pack time system will pick up from shipping point Transportation time ( Trans lead time+ Transit time ) is from Route. Transit time means travel duration time..
Delievry scheduling will be started only from the material availability date i.e., system will first determine the material avail date and then do scheduling. By default Standard SAP system does Backward Scheduling in case material availability falls beyond the required delivery date system will do forward schedluing
Delivery Scheduling consists of the following Basic activities:
We give deatils while creating order:
Order Creation Date
Required Delivery Date
Order date - Material availability date - Transportation Planning Date - Loading date - Goods Issue Date - Required Delivery Date
Time Between GI Date and required Delivery Date is called Transit Time
Time Between LoadingDate and GI Date is called Loading time
Time Between Material Availability Date and Loading Date consists of 2 components - Pick / PackTime and Transportation Planning Time
System has to calculate all this before it determines the confirmed delivery date
Regds
MM
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.