Dear All,
I am creating Inquiry with VA11 and assign it to one WBSE which is Billing Element and Assign DIP profile to it.
I want to create Quatation and Billing Plane for that with the refrence of that inquiry .
When i use DP81 it shows the error message (Expendature items not found).I am sending the full error message as given below
No expenditure items found
Message no. VPK1310
Diagnosis
No expenditure items matching the selection were found.
System Response
No processing possible.
Procedure
Resource-related billing contains no expenditures for the posting timeframe you specified. Specify a different timeframe.
In the case of quotations, there are no costs in the project or service order. Check whether any have been planned.
Not able to understand the Time Frame .
And for Qutotation there is price in Inquiry.
Please help me in doing same.
regards.
Sukhveer.
Dear,
Its problem of SD side time frame is not defined there.
Its answred.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You need to have cost planned for the WBS Element. This cost plan can be automatic or manual. Only then you can have sales pricing.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
OK. Now check the timeframe. Go to one of the PS reports or even RRB reports and check during what period you have carried out cost planning. Please let me know during what period you have carried out cost planning and what is the procing date you are selecting on DP81 initial screen. I also hope that you have done details cost element based cost planning.