on 09-02-2008 6:53 AM
HI Friends,
Any one give me some idea about LTP scenario for Cement mfg industry. Clint wants Long Range prod. plann for Materials and capacities. How is it help this LTP for this business area, give me an elborate idea.
Srni.
Dear sapguru,
Generally LTP is carried for selected Finished products,that too in the Financial year begining,for budgeting
purpose.There are companies who use this LTP as pre planning tool for production.
Say they check the capacity availability for next 3 months,materials requirements etc.
Per hour activity rate can also be derived using this LTP.
After carrying out LTP run,we will get simluate planned orders,which cannot be processed for further
actions like converting into production.Purchase order.
Important settings are in T code - OPU5 - Scheduling Planned orders for LTP,Here itself you maintain the
planning scernario for individual plant.
1.Demand will be given in MD61 for the products for which you are planning to carryout LTP in non active
version,that's other than 00 and also remove tick mark against the check box for active in MD61 screen.
2.Mention the planning scenario which's been configured in MS31.
3.Assign the plant and Planned independent Requirements in MS32.
4.Planning file entries in MS20 and display it in MS21.
5.Carryout LTP run in MS02 and the simulated planned orders can be checked in MS04.
6.capacity requirements for LTP can be viewed in CM38.
7.Transfer of planned activities to production can be done in KSPP.
I hope to some extent this will help you.
Please check this link for further understanding.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In LTP a planning scenario is created to enable simulation of material requirements which can be based on the production plan. Planned requirements can be reviewed and adjusted as needed. Once the simulated requirements are accepted, the demand (independent requirements) is then transferred to active demand management.
A detailed Capacity situation can be seen for any scenario which is used to evaluate LTP scenario as well as production plan.
Steps,
Create Inactive Demand in Demand Management MD61
LTP Planning Scenario MS31
LTP MRP MS01
Capacity Planning CM38
Copy to Active Demand Management MS64
To analyze long term planning use,
item : MS05 - MS06 - MS44 - MS47
purchasing : MCEC - MCEA - MCEB
stock - MCB)
Hope clear to you.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
This long term planning is used for the planning of the materials more than 6 months.
This is simulative planning which used by creating the scenarios.
Whenever you feel the perticular scenario will be mostly matched with requirements of the client, you will transfer that planning to Active planning(mrp).
IMP Tcodes for LTP:
Create planning scenario MS31
Planning Run MS02
MRP list MS05
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.