on 09-01-2008 10:17 AM
Hi,
I have created a project and a few WBS elements below that which all were actuals elements. I now want to now change the WBS element to statistical and it does not allow me and the tick is grayed out. Could someone please suggest a way that could achieve it.
Regards,
Roville
Dear,
If any transaction done in that element then you can not change it.
To create it as statistical you have to first transfer all amount to other element then you change it.
Hope above will helpful.
GOPAN