Shut down maintenance

Former Member
0 Kudos

Hi,experts

Can anyone please tell me how to address shut down maintenance (like half yearly,annual shut down etc.) in PM module??? thanks in advance.

rgds

rajib

Accepted Solutions (1)

Accepted Solutions (1)

former_member187991
Active Contributor
0 Kudos

hi

Can you explain briefly of your requirements of shutdown maintenance ,

it can be segregated using Maintenance activity type. preventive maintenance using maintenance plan and also revisions

regards

thyagarajan

Former Member
0 Kudos

Hi,

Actually, we do not have PS module.Our client's requirement is to plan shut down maintenance of some equipments and they want to capture the cost equipmentwise specially for shut down maintenance.can anybody please guide how to map this in SAP???thanks in advance.

rdgs

rajib

Former Member
0 Kudos

Hi Rajib,

First create Mintenance activity type and assign it to all order types as Shut down.

Then either thro preventive maintenance you generate shut down orders or select pending orders from IW38 T code and assign pre defined revision to orders and maintain Maint activity type as shut down in those orders.

You will get equipment wise cost based on maintenance activity type Shut down in the report MCI8 PM activity type.

Hope this will help you.

regards,

N.Nagaraju

former_member661658
Discoverer
0 Kudos

This message was moderated.

Answers (3)

Answers (3)

Former Member
0 Kudos

thnks everybody

rgds

Former Member
0 Kudos

Hi

If you want to tag the work orders for executing them during the shutdown you can use the functionality of assigning 'Revision'. You can then search all the orders with that revision number those are pending to be executed during a particular shutdown. It also becomes handy in case if there is un-planned shutdown of the plant and you need to identify what are the pending orders those can be attended.

Regards

Former Member
0 Kudos

Rajib

It depends upon what u want to achieve.

If it is for thorough Project , you can use the functionalities for PS module & integrate the Maintenance Orders with the activities of Project

If it is required to be differentiated as Shutdown work for analysis only then create separate activity type for shutdown

Like I said , it depends on your needs

Regards

Jignesh