Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Balance in 1 currencies at the time of settlement of WBS to cost Centre

Hi,

while settling the WBS to cost centre I am getting this error in IDES for CO Code1000.

Balances have been found in 1 currencies with the following details:

Currency type Amount Currency

40 0.04 USD

(A maximum of three differences are listed)

Pl suggest what to check

Thank You.

Regards

Man

Former Member
Not what you were looking for? View more on this topic or Ask a question