PO user exit for payment terms release strategy

Former Member
0 Kudos

Hi friends,

My requirement is to any changes to Payement terms in PO should trigger the re-release of the po....

Plz. explain... How to proceed...

which user exit i have to use........

Thanks in advance,

Navin.....

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

My requirement is after changing of payment terms my release strategy is not changing for released po... i want to reset it for re-release after changes made to po changes....... which user exit i should should......or any other alternative....

Rgds,

Navin

deiva
Active Contributor
0 Kudos

Standard release strategy is applicaple only for Value changes in the released PO. So if u want to trigger the release strategy for any other changes then do the Workflow configuration. It can't be done thro' User exits.

deiva
Active Contributor
0 Kudos

Hai,

This can be mapped with the help of Work flow configuration.