on 09-01-2008 3:35 AM
hi
As we know, the production order of finish goods includes started date and finished data such as Sep 1, and Sep 10. So, MRP calculate component requirement which includes delivery date such as Aug 28 (because of lead time).
however, purchase people hope to deliver these components day by day. fox example, total delivery Qty maybe is 1000ea. this production order needs to be produced in 10 days. so, the components should also be delivered 100ea per one day.
however, purchase order just include a delivery date. which have no detailed schedule.
anybody can tell me how to meet this problem?
Henry
Hi
For this, you have to split the requirement quantity of the finished product day wise.
Then if you run MRP, system will create procurement proposals (Purchase requisitions) day wise for the raw materials.
Regards
Bala
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Bala
I need to go to operation view. thanks
BR
Henry
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Bala
I have see the split menu bar in production order. however, this bar is inactive in my SAP system.
could you please tell me how to use this menu bar?
Henry
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The order split is not allowed with the following status:
Created, delivered, finally confirmed, locked, technically complete, closed, deletion indicator set.
An order split is allowed with the following system status:
Partially released, released, partially confirmed.
Please check and come back.
Regards,
R.Brahmankar
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.