on 08-31-2008 12:14 PM
Dear All,
We have a problem when there is a delivery from projects(CNS0).When we are running the transaction CNS0 and entering Qty 7, and creates delivery, system generates a Delivery Number and takes us to VL02N where we enter batch,picked qty and storage location.Here we find delivery quantity 7 by default and if we change the quantity from 7 to 10 even then system accepts more quantity as it checks the project stock.
We want system should not allow the delivery quantity more than the quantity specified in the CNS0.
We are not creating sales order as we directly delivering from projects.
In the previous case,as you suggested we made the changes in delivery item category,but the same logic is not working here as it is without sales order.
We are using item category DLP and Delivery type is LP.
Request you to provide your valuable inputs
Thanks in advance
Regards
Muzamil
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.