Replenishment Lead time calculation for availability check

Former Member
0 Kudos

Hi experts,

based on SAp documentation Replenishment Lead Time during Sales Order Item availability check is caclulated for externally procured materials using these lead times:

o Purchasing Processing Time

o Planned Delivery Time (MRP I view)

o Goods Receipt Processing Time (Purchasing view / MRP I view).

Can you tell me please where it is maintained the Purchasing Processing Time?

Thank you very much

Kind Regards

Andrea

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi there,

in MM02 / MM03, material master, MRP screens you will find GR processing time & planned delivery time.

Pls check to see if there is any in MM Purchasing area.

Regards,

Sivanand

Former Member
0 Kudos

Hi Sivanand,

thank you for your answer.

Planned Delivery Time (MRP I view) and Goods Receipt Processing Time (Purchasing view / MRP I view) are ok into material master.

No there are no Purchasing Area.

Kind Regards

Andrea

Former Member
0 Kudos

Hi there,

Pls check in SPRO --> MAterials Management --> Purchasing.

We dont maintain the purchasing data in SD. So it should be maintained in MM purchasing.