Dear Experts,
I have created a Project and network through Sale order (assembly processing) and a milestone has already been assigned with network activity.
Now when a billing document is being created (after delivery) system is allowing me to do so inspite of non confirming the milestone, in my opinion the same should be put in block till the confirmation has been received from PS via milestone
Kindly suggest what step/configuration i have missed out
Suitable suggestion will be rewarded please
Regards,
Pawan Khurana
Dear,
Billing date is appended as milestone is confirm manully or automatic .If milestone date reached then Milestone can also confirmed .
So please check the milestone date.Or milestone is confirmed.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Not very much confirm....just check which billing plan type you have selected.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.