hi,everyone. i'm a green hand in PS.
i know Statistical wbs element is different from normal wbs element from you guys.
but i don't know how to set a Statistical wbs element, i mean how to make a normal wbs element become a Statistical wbs element?
regards,
tiger wu
Go to Tcode OPSA - Select your project profile - Go to Controlling tab - Tick Statstical check box -Save.
Create WBS using this project profile.
Hope it helps.
Arya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
There are two methods
1.If you want all the WBS in the Project Structure to be Statistical WBS then do The settings in the Project Profile
2.If you want Selected WBS to be Statistical WBS-While creating Individual WBS Elements Go to "control" tab page (ie the 4th Tab )in WBS detail Screens and set the box "Statistical".
You also need to give a Cost center for this Statistical WBS where the actual will be booked in the same screen
Hope this will help you
Ssk
Yes, if you choose this (in which the Statistical check box is ticked) to create a project, all the WBS will be statistical.
To create a project in which some of the WBS are statistical and some are not, you don't need to configure this (check Box) in Project profile. You can create a project (CJ20N) and for WBS elements on control tab, you can check this or leave it.
Hope it helps.
Arya
Edited by: Arya Singh on Aug 30, 2008 8:09 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Points?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.