Reporting in PS on multiple project

Hello,

I am searching for a report to analyse the margin of all the project currently open on our SAP.

(with the cost, revenue, budgeted cost and revenue).

I have found report doing that (for example in PS91) but for specified WBS elements or project.

How can I do that on all opened project in the database ?

Additional question : If a user request a report on PS would you say that most of the time it's already there in the system or that most of the time a development is needed ?

Thanks for your answers,

Manuel

Former Member
Former Member replied

Would like to suggest you to try CJI3 and CJI8 for Actuals (Cost and Revenues) and Budget respectively. To compare both actuals and budget together in a report you can use S_ALR_87013558.

What you mean by Open projects? Put Asterik (*) and run for all if you want to see all of your projects.

It depends on the request of the user, what report they are looking for, there are lots of good reports available in PS so you might want to go through Information systems of PS.

Hope it helps.

Arya