I have two questions, when MRP taken place will that take place at Plant level or Storage location level?
Can we make that to limit to some storage locations only?
Because i have requirement from business that, in one plant they have 5 storage locations but they want MRP to happen to check the stock levels in only in one storage location.
How can we configure this?
Thanks
Sundu
Hi,
MRP run is possible at plant level or at MRP area level. You cannot run it at SLoc level unless you assign one SLoc to an MRP area and carry out an MRP run for that MRP area.
You can exclude SLocs from MRP planning.
Please check these links:
http://help.sap.com/saphelp_47x200/helpdata/en/f4/7d2d2644af11d182b40000e829fbfe/frameset.htm
http://help.sap.com/saphelp_47x200/helpdata/en/c4/106956ae8a11d1a6720000e83235d4/frameset.htm
Csaba
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
105 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.