Confirming subcontracting PO's in SRM

Former Member
0 Kudos

Hi Experts,

Did any of you managed to confirm a backend subcontracting PO in SRM using transaction BBPCF03?

Confirming non-srm backend PO's is possible within the standard, but when I try to confirm a subcontracting PO the system issues the following message: "PO contains no items for confirmation".

I managed to confirm 'normal' backend PO's.

Thanks for your help!

Regards,

Martijn

Accepted Solutions (0)

Answers (1)

Answers (1)

harishsarathy29
Active Participant
0 Kudos

Hi,

To my knowledge, Subcontracting process is not supported in SRM and hence you face this problem.

In any case Subcontracting Orders should have a transfer posting through mvmt type 541 for input components i.e(Send materials to vendor) and only then GR could be posted for the finished component.

Hope this helps.

Regards

Harish