on 08-27-2008 1:01 PM
I get the message "Corrected deliveries cannot be changed" when trying from vl02n to make the PGI. Why? Can anyone help me?
Hi,
Good Day,
May Help you below info,
You must then check the cumulative (delivered) quantities, because the changed fiscal year variant may have led to a u201Cshiftu201D in the cumulative delivered quantities(Sum of all deliveries made in the customer fiscal year).
If you see that the cumulative (delivered) quantity is no longer correct, you must either enter the corresponding cumulative correction quantity in SAP APO or create a correction delivery in SAP R/3.
for More Details
[http://help.sap.com/saphelp_scm41/helpdata/en/50/0d89f2ad919c40b95b9ae7583c8c96/content.htm]
All the Best
Best Regards,
KSK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
10 | |
5 | |
5 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.