We are taking a MRP run on Project.While doing so system generates Network order for the Header material for which I mentioned strategy as 85-Assembly processing with network/project.We want system should generate the Planned order with the same stategy to the material so that further processing should be in PP module.
Is it possible to convert network order into planned order ? if yes then pl guide.
Rgds
Edited by: Shrikrishna Rasam on Aug 27, 2008 1:19 PM
Edited by: Shrikrishna Rasam on Aug 27, 2008 1:29 PM
Hi,
You need not convert network order to PP order. Configure assembly processing such that PP order will get generated when sales order is saved.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
Thnks for the inputs.
Currently we are crating production order manually but it is an added acivity and we are thnking to avoid it.
How the production person could be initiated ?
How we can stop further processing of bottom level planned order until the Top level production order is not created ?
Rgds