Dear Expert.,

Below is my client current system set up

A. CN08 -Allocate Material to Standard Network

Material Order Type Std Network Profile Std WBS Element.

XXX 001 1000 F-00004-1

B. CN02 - Standard Network 1000

Int. Activity Operation Std WBS Element

10 Molding F-00004-1

20 Scrapping F-00004-2

30 Polishing F-00004-3-1

etc.

C. VA01- Sales Order (SO) creation

System create Sales Order NO.and at the background it create also Project No.

Eg. SO - 6160 Proj Def. - S-6160

D. CJ02 - Change Project

Level WBS Element Description

1 F-6160-1 Molding

2 F-6160-2 Scrapping

3 F-6160-3-1 Polishing

Question : If i will make a BOM with the structure below

BOM - XXX

Component - Material No -

1000 Molding

2000 Scrapping

3000 Polishing

Is there a way i can configure the system that when it create SO, PS will still be created on background

but also a WBS BOM will be created automatically also ?, if in case, how this will be done?

CS73 - WBS BOM will be like

WBS Element - F-6160-1

Material - XXX

Plant - PL01

BOM Usage - 2

Hope anyone will be able to enlighten me on this.. Many thanks in advance.

Rgds,

She

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

in my knowledge assembly processing cannot automatically create WBS BOM - for this you will need to investigate development work

Answers (0)