on 08-26-2008 10:20 AM
Hi
CM53 and CM32 are capacity evaluation and levelling for WBS element. But eventhough system is giving a list of production orders on executing a WBS element, inside under WBS element field in the planning table it is blank and not showing anything. When checked the assignment in the production orders WBS is there. So why it is not coming in planning table. If it will not come then what is the use of that?
Pls suggest
Thanks & regds
Hi
When I check CM32 for a WBS element, inside the capacity planning table list of orders are coming wrt the WBS no. In these orders system is displaying WBS element for network orders only and not showing for production orders. Why is it like that? Shall I have to do any setting for production orders? Pls advise.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.