Hi,
I am facing an issue w.r.t. distribution of Planned material cost in Project. Materials will be procureed from Projects for which the same is assigned to network activity of the Project. This will lead to planned cost of the Project. The requirment is the planned cost should be equally distributed fot that entire period of the Procurment & not single period. Right now, the Project cost is obtained on the material requirment date only. This will lead to fluctation of Project profitability.
Please advise me on this.
Thanks.
Hi,
In case of non stock material, maintaining an invoicing plan will help you distribute costs over period. For stock items, you need to stick to start or end of activity.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.