on 08-25-2008 6:53 PM
Configuring ChaRM in spro.
when I try to activate BC Sets I get an message:
"There is a production client in the system. SAP Change Request Management cannot be configured"
This is our production instance, and we have no dev or qa system, so we have no way of transporting in changes. The system is currently only used for Central User administration.
We plan to create a dev and qa system, but we need to get ChaRM up and running first.
Is there any way to get around this message?
Thank you!
can you just change the client role in SCC4 to Dev?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I had the same issue and followed the steps stated above. I changed the Production client role to be Test, activated the BC Sets, and now am trying to change the Production client role back to Production. I am able to do that in SCC4, however in SMSY the client role still appears as Test. Can anyone help me please?
Thanks,
Shawn
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
we changed the system to test, activated the bc sets and set it back to production.
there were no problems.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
That is my thought also, I am just concerned that changing the client to Dev and then back may cause problems in CUA.
Does anyone have experience doing this?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.