Assigning Materials directly to wbs

Former Member
0 Kudos

Dear Experts,

I wanted to know that if is there any way or alternative wherein i can assign a material to a WBS element and from there i allocate those material to activities which are assigned to my WBS via network or directly.I hope i can get some lead fromyou all.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You cant assign material to WBS. As per my opinion WBS is a cost object which plays a role in controlling the project whereas material is part of logistics and rightly should be assigned to network activity which control the project from logistics point of view.

Regards

Answers (4)

Answers (4)

Former Member
0 Kudos

144169 - FAQ creating commitment items

151551 - FAQ scheduling of networks

189230 - FAQ progress analysis

360584 - FAQ mta (milestone trend analysis)

417511 - collective note for PS cash management

428728 - FAQ resource related billing

440186 - FAQ 2 validation and substitution in PS

504180 - FAQ system status PTBL in resource related billing

522581 - how to implement user-defined fields

528604 - FAQ billing and costing RA

544123 - FAQ resource related billing and RA

545095 - FAQ resource related billing, accrual, quotation and RA

553661 - FAQ coding masks

553832 - FAQ WBS element number conversion

554139 - FAQ batch input

554415 - FAQ authorization check

569048 - FAQ user status

570330 - FAQ customer specific fields

570471 - FAQ confirmations in PS

573077 - FAQ archiving PS_PROJECT

573133 - FAQ opening or calling a network

579761 - FAQ OpenPS for Microsoft Project (OpenPS4MSP)

583698 - FAQ note - MS access interface

594809 - collective consulting note for PS confirmation

668240 - FAQ hierarchy reports

668513 - FAQ cost element reports

668514 - FAQ line item reports

677169 - FAQ material requirements in PS

678522 - FAQ data inconsistencies in PS

700665 - FAQ planned revenues from sales documents

700697 - FAQ logical database PSJ, selection in the PS infosystem

700700 - listing of all PS FAQ notes

700875 - FAQ structure and individual overview reports

701075 - FAQ PS cash management

701076 - FAQ PS summarization

701077 - FAQ PS period end closing

702965 - FAQ project planning board

858877 - FAQ resource related down payment processing

1108787 - FAQ PS archiving

Former Member
0 Kudos

OK i understand that there are limited ways to attach materials to a WBS element i would like to thank all of your for your valuable inputs.

Former Member
0 Kudos

Other than easy cost planning you can not have direct assignment of material to WBS Element. But in case you want to make material purchases and do not want to have network and activities then you should directly create PR against the WBS Element.

virendra_pal
Active Contributor
0 Kudos

only if you use easy cost planning it will be possible to assign materials to WBS