on 08-25-2008 1:10 PM
Hi,
We are implementing SRM5.0 with ECC6.
When we create PO manually in SRM then it does not goto R/3. Here PO status remains in Order condition but there is not document transfer from SRM to ECC as well as when we tried to push through FM, it gives following errors;
1.BBP_ANALYZE_PO_APPLIC is not released
2. PO XXXXXXX : No instance of object type purhcaser order has been created, External Referance.
We have already checked all settings for ECPO as well as backend document type.
We can create PO by normal cycle like SHC--->PO its goes properly in ECC
When we create Manual PO and click on Order as direct material then also SRM PO goes to ECC properly.
Only we are facing problems to transfer SRM PO which created manually to ECC. (Note - This process was also working fine before few days)
Any idea?
Thanks,
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jason,
Any information regarding this?
Thanks,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
What was the last status of PO in BBP_PD
Can you create one PO and try to pull in development server and try to see any dump .
Check all rfc connections are worjking fine.
Which FM you are using to push the PO from EBP to R/3.
regards
Muthu
Edited by: Muthuraman Govindasamy on Aug 26, 2008 7:12 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.