Hi all,

I created a sales order 10 qty.The confirmed quanity is zero since there is no stock.I run MRP so that the PR generated for 10 qty.Now Is it possible to confirm the schedule line 10 quantities in the sales order through back order processing.

In sales order change mode I am able to create new schedule line or edit the existing schedule line.Is this the only way?

please advice.Goods answerd will be rewarded

Regards

Mano

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Mano,

try using V_V2 transaction and reschedule.

regards

Biju