Exception & Rescheduling date in MD04

Former Member
0 Kudos

Hi all,

Can anyone explain what is exception in MD04 screen.PR generated automatically for the unconfirmed schedule line quantities in the sales order.The exception 30 is automatically proposed by the system.How is it?

Please expalin the rescheduling date also

Regards

Mano

Accepted Solutions (0)

Answers (1)

Answers (1)

roger_white2
Participant
0 Kudos

Hi,

MRP Message30 = Plan process according to schedule.

This means that all the requirements as calculated during the MRP run are satisfactory and that the process can continue.

What to do:

Proceed with the process; i.e. convert the planned order and purchase requisitions.

Regards