Former Member
0 Kudos

Hi

I am creating purchase order for raw material with Acct assignment as P.

While doing so when any material with G/L account as which has account group balance sheet Account system doesn't check the budget though availabilty control is active.For the services and other material system checks the budget.

With the account assignemt Q - Project stock ..system doesnt check the budget.

I want to put budgetory control for such material with account group as Balance sheet item. How to achieve this ?

Pl suggest.

Rgds

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

check wether said costelements are budget exempted (Tcode: OPTK).

regards

murali

Former Member
0 Kudos

Hi ,

Thnks for the prompt reply.I checked as u said but none of the cost element is budget exempted.

Rgds

Former Member
0 Kudos

T code OBYC, click on Transaction BSX to get the list for all the cost elements for the valaution class used for material in master.

T code KA01, create these cost elements with cost element category 90, i.e balance sheet account.

Regards

Sreenivas