on 08-24-2008 7:59 AM
HI
i have an issue with a s cenerio
we have done PO then we hve done outbound delivery wrt PO but when we do shipment ,in that we have selectd check in and planning tabs
but issue is we are not able to select shipment completion tab , as we save it
it remins unseleted
as we do it it would be posting a GI
it is nit getting selected
earlier we have selected shipment start/end and then shipment completion
when we save it only shipment start / end buttons are remaining selected ..
shipment completion button remaining unselected
Awarded suitable points for right answer
warm regards
adarsh
Closing this thread
Answer is Posting period was closed for the delivery connected with the shipment
So posting period has to be reopened to proceed futher
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI All,
Thsi issue i have got it resolved by Myself
It is due to Posting Period was closed that's why
Shipment completion tab was not getting selected
regards
Adarsh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.