MRP can be configured not to run for a line item

Former Member
0 Kudos

Hi Folks,

I have a question... Scenario is like this:

We are getting a Sales Order in SAP from a Portal which is exposed to external customers. The Sales Order has say 10 line items. Usually this will kick off MRP for each of these line items right away. Now we do not want MRP to kick off as we do not know as yet the line items in there are valid or not. There is another application which will confirm if the line item is valid or not. Once it confirms if the line item is valid the MRP will run for only those items which are valid and rest of the line items will be rejected.

Question how we can stop the MRP to not to run for the for the line item once the sales order is created. Creating a Delivery block is not going to help in stopping MRP run...

Looking for some out of the box solution without any customization.

Thanks and Regards

Roger

Accepted Solutions (0)

Answers (1)

Answers (1)

roger_white2
Participant
0 Kudos

Hi,

Check your requirements class via transaction OVZG. Do they have automatic planning set? Is No MRP Set?

Regards