on 08-22-2008 11:08 PM
Hi Solman experts,
I have a question. Is CHaRM possible in a 2 system landscape without creating extra clients? For example:
BWDEV100 -
>DWPRD100
Thanks in advance.
Regards,
Ricky
Hi,
Yes, you configure for 2 system landscape for ChaRM in SOLMAN.
1. BWDEV100
2. DWPRD100
Regards,
Srini Nookala
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Andy,
Make sure that your transport route is client specific(for the 2 system landscape).Once that is done,creat a logical component with your dev and pord system.Include that logical comp to the maintenace project and create the maintenace cycle.Now you will get a maintenance cycle with sourse system and production system.
Revert for any clarifications,
Avinash.
Hi Avinash,
But in TMS do you create one delivery transport route from dev100 to prod100 or do you create a consolidation route to prod100. Usually in a three system landscap you create 2 consolidation routes to the test system one with a transport layer that you created and one with the sap transport layer and then one delivery route to the production system.
Could you please explain what kind of transport route you create?
Thanks in advance.
User | Count |
---|---|
84 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.