Hi CHaRM-experts!
I would like to know whether or not is it possible to use the Change Request Management scenarion for only one productive system?
It means we have systems and cases where we should apply the emergency correction only in productive system, without any transport from DEV or QAS system.
Does ChaRM support such case?
Thank you very much!
regards
Thom
They are called Administration Tasks. You still create a ticket but it is not associated with a transport request.
There isn't much info on it but this will get you started: http://help.sap.com/saphelp_sm40/helpdata/EN/dd/cc86a571464559a2685a404397065b/frameset.htm
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Are you applying a transport to your production system? If so, where is the transport coming from?
From what you have written, it seems you are doing u201Chands to keyboardu201D directly in production.
Regards
Don
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
82 | |
10 | |
10 | |
9 | |
6 | |
6 | |
5 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.