Former Member
0 Kudos

Hi all,

What is the difference between the availabilty check in sales/general plant view and the MRP 3 view

Regards

Mano

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi

Availabilty check in MRP3 is based on strategy group and in sales general plant we give availability check group 01(individual),02(collective) at material (sales general/plant),which inturn assigned to check rule(availabilty check control) tcode ovz9.

cheers

B.S Goud

Former Member
0 Kudos

Hi,

MRP3 is used for PP purposes.

Checking Group for Availability Check

This field has two uses:

1. Specifies whether and how the system checks availability and generates requirements for materials planning.

2. In Flexible Planning, defines - together with the checking rule - the different MRP elements that make up this key figure. The sum of these elements gives the key figure.

Use 1: Availability Checking and Materials Planning

Use

The value you enter for use 1 (see above) is a default value which defines:

Which MRP elements (for example, purchase orders, reservations) the system includes in the availability check

Whether the system checks availability only until the end of the replenishment lead time or whether it checks availability over the entire period for which MRP elements exist

Whether the system generates individual requirements or summarized requirements if you enter sales orders or deliveries for the material

Use 2: Flexible Planning

Dependencies

If you use this field to define the MRP elements of a key figure for Flexible Planning, you must also select Document KF in the Customizing parameters of the information structure.

Thanks,

Raja

Former Member
0 Kudos

Hi,

Both are the same.

Hrishi