Reference point

Former Member
0 Kudos

Hi Friends,

Hope all are doing well,

I hv one doubt.

We maintain the reference point in network activity(in assignment tab) for BOM transfer.

When I am going to enter any value suppose A there I am getting the error as

Entry A does not exist in TCNRFP --check entry.So now

I want to ask that whether reference point is maintained by PS person if yes then how can I do this and if not then what I shud do?

Help will be rewarded.

Regards

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

ansd

Former Member
0 Kudos

Hello Amit,

It is required define reference points in customizing before using the same in application.

Only those reference points are allowed for useage. However, you are free to use same reference in multiple projects.

Path is SPRO--- Project Sys -


Material --- Bill of MAterial --- Define reference points for BOM transfer.

However, there also provision to define user specific fields as reference points. Any field which is common in activity and BOM item level can be used. Should define it in customizing.

Path is SPRO--- Project Sys -


Material --- Bill of MAterial --- Define field in BOM and activity as reference points.

Example: can be Sort string or any other field.

Thanks

Saikishore Ganga.

Former Member
0 Kudos

Hi Amit..

Reference Points are maintaind by PS Consultants..in BOM and in activity ......(See IMG->Project System->Materail->Bill of material ).......

if you want to see the data in a particualar table --use t code SE16..

Rewards points if useful

Regards

Rama Shanker Sharma