Hi Experts ....
I want to calculate Progress in my project.....I studied the Cost Propertinality method from help.sap.com...but most of places I confused .....I have calculate progress data according to as I under stand ...please clear me ..my concept is clear or any other place i am doing wrong....
Overall Plan Cost 100000
For Four Periods i devided the plan cost and actual cost 25000 , Equal for all periods.
For Period 1st
Plan Cost 25000
Actual Cost 20000
Overall Cost 100000
Plan POC (Plan Cost for Period 1/Overall cost)%
so Plan POC (25000/100000)%=25%
Actual POC (Actual Cost for Peiod 1/Overall Cost)%
So Actual POC(20000/100000)%=20%
Now BCWS= Plan POC * Overall Cost=25%*100000=25000
BCWP=Actual POCOverall Cost =20%100000=20000
ACWP=20000
For Pwriod 2
Plan Cost (Plan Cost for period 1Plan Cost for period 2)=2500025000=50000
Actual Cost (Actual Cost for Period 1Actual Cost for period 2)=2000019000=39000
Overall Cost =100000
So Plan POC=50000/100000=50%
Actual POC=39000/100000=39%
Now BCWS=50%*100000=50000
BCWP=39%*100000=39000
ACWP=19000
is this right concept ...please clear me I am taking right values for ACWP?
if anybody has some supportive data please share with me at ramas dot sap at g mail dot com
Thanks & Regards
Rama S
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You understanding is correct. Ensure the system behaves same.
Thanks
Saikishore Ganga
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.