on 08-22-2008 10:09 AM
hi everyone,
i am creating workcenter in project systems. the standard value key does not appear in basic data view of work center.
i want to assign parameters for a work center.
can anyone help me on this
thank
sanjeev
Hi
Check the work centre catg at the time of creation. If it is 0001 then it will allow the Std Key. Otherwise you need to enter it in a next screen
Srinivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
This feature may not be relavent to PS work centers. This is my guess.
If you try to create non-PS WC in tcode CR01, the reqd field appears.
If you try to create PS WC in tcode CNR01, the reqd field doesnt appear.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.