How to create Delivery for Scheduling Agreement

Former Member
0 Kudos

Hi experts,

I have created scheduling agreement with DS as document type.Now i am trying to create delivery for that with VLO1N tcode. But i couldn't able to do that. Is there any solution for that or i am wrong? please throw some light on me.

Thanks,

Kanna.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi kanna palle

First u have created Schedule aggreement and when u raise a sales order, with reference to schedule agreement. then automatically the schedule agreement data will trigger in to sales order. then u can do delivery easily..(vl01n)

Former Member
0 Kudos

Hi experts,

when i saved schedule agreement its saved perfectly saying "scheduling agreement is saved 30000053" , but when i go back to see that document in VA33 , it is saying " scheduling agreement 30000053 is not in database or not been archived".

How to come over this , I ve checked copying controls , they have been maintained correctly from source-DS to target LF.

I have found this below description in LOG

SD document 11882 is not in the database or has been archived

Message no. V1302

Diagnosis

This message is issued if no document header (VBAK) can be found

(discrepancies in R/3) for a sales requirement single record.

System Response

In the initial sales order supply, the following error message appears

'Document xxxxxx not available' V1 302.

Procedure

If an error occurs in initial data supply in APO, discrepancies have

occurred between the requirements and sales documents in R/3. This

discrepance can be corrected in R/3 using report SDRQCR21.

Let me know if i have to check anything else.

Thanks,

kanna.

Edited by: kanna palle on Aug 23, 2008 9:31 AM

Former Member
0 Kudos

Hello,

Do you face any update terminated message after saving the scheduling agreement?

Prase

Answers (2)

Answers (2)

former_member550050
Active Contributor
0 Kudos

Scheduling agreements contain Fixed delivery dates and fixed quantities

The word Fixed carries a lot of meaning here

These dates are available in the schedule lines of your scheduling agreement

Once dates are due, in the delivery due lists you can see your scheduling agreement

In scheduling agreemement the subsequent process is delivery

Scheduling agreement means scheduling your deliveries

You can also do delivery by vl01n transaction on that particular due date

Pls check whether you are creating delivery on the due dates displayed in the schedule lines of your scheduling agreement

Raja

Edited by: ramanathan raja on Aug 22, 2008 2:09 PM

Former Member
0 Kudos

Hello,

Could let us know the error?

Prase

Former Member
0 Kudos

Hi ,

The error what i am getting is SALES ORDER 30000033 DOES NOT EXIST.

Thanks,

Kanna.

Former Member
0 Kudos

Hello,

Check the delivery type you have selected in VL01N. Also check the copying control between the Scheduling agreement type to the delivery type in VTLA.

Prase