how can the delivery dates be changed

Former Member
0 Kudos

Dear all

My company has gone live 1 month before,

we transfered the data from legacy system to R/3,but we have a problem that is the delivery dates for the months of may are being displayed for june and july,

Invoice dates are correct i.e in the month of may ,

how can i revert the dates back to the delivery dates to the month of may from june and july,

Regards

Mohammed Raees

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

If I understand correctly, while creating the old deliveries in the system you are getting current dates? In case you are manually entering the information, and the deliveries haven't yet been invoiced, you can go to the delivery doc (TCode; vl01n) and change the date manually.

In case the delivery has already been referenced (invoice generated from it), cancel the invoice and then change the dates.

Cheers.

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear All

how can a delivery be restricted or blocked untill the PGI is done

With Regards

Mohammed Raees