on 08-21-2008 1:47 PM
Dear all
My company has gone live 1 month before,
we transfered the data from legacy system to R/3,but we have a problem that is the delivery dates for the months of may are being displayed for june and july,
Invoice dates are correct i.e in the month of may ,
how can i revert the dates back to the delivery dates to the month of may from june and july,
Regards
Mohammed Raees
Dear Mohammed
No it is not possible to change the delivery date which has already been PGId and that too two months back. Standard will not allow to open the MM periods for May and June now.
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
THANKS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello !!!!
it is not possible to change the date. In standard Sap u can only open one months posting period. so it is impossible & once again to open the posting period only few people have authorization.
hope it will help uds
regards
Dibya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.