Hi All,

We have the following problem in cost assignment in shopping cart: We can choose different cost distributions: 1. by percentage; 2. by quantity; 3. by value. When choosing 3 - "by value" and distributing values to different WBS-elements with budget check, system comes up with several error messages saying budget overspend, also we exactly fill in the open budget on theese WBS-elements. The main reason for this seam that our backend system R/3 4.70 just knows the two posibilities 1. - by percentage; 2. by quantity.

Do you guys know a possibility in customizing or elsewhere to deactivare the possibility 3 - by value, since I think back end can not work with this kind of distribution.

Best Regards Thomas

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member183819
Active Contributor
0 Kudos

Hi

Do you want to remove the drop down by value in the shoping cart screen ?

BADI - BBP_UI_CONTROL_BADI - method BBP_SC_UI_CTRL field control You may try here

regards