on 08-20-2008 11:26 AM
Hello PS Gurus,
In my bussiness process, customer places an Sales order w.r.t Quotation. Now here we use project systems to manufacture the product. I am trying to use Assembly processing for the same process. But the problem is, in Sales order there may be one or more line items with different specification & quantitys of similar project structure. Now what I need is for each line item in sales order system should create project structure useing assembly processing.
Is this possible? if yes what settings are required?
Thanks & Regards,
Tushar Patil
Hi,
In any case, only one project will be created for one SO via Assembly processing. SD-PS indicator will ensure different roots in same project. For eg in case of 'n' line items in SO, project with 'n' root level (1st level) elements will get created.
If you wish to use SD-PS indicator, ensure that your project profile allows multiple roots. In OPSA, 'Only one root' must not be ticked.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
go thru following links
http://help.sap.com/saphelp_46c/helpdata/en/95/1613a8837b11d2b6700000e82d8bd1/frameset.htm
sales item wise WBS elements can be triggerred from Sales order to Project structure.U have to assign the Material no to standard WBS in CN08.
Rgds
Edited by: Shrikrishna Rasam on Aug 20, 2008 2:08 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Yes it is possible...check cj92 in "control data" there is a a check box SD/PS assignment.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
90 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.