Hello PS Gurus,

In my bussiness process, customer places an Sales order w.r.t Quotation. Now here we use project systems to manufacture the product. I am trying to use Assembly processing for the same process. But the problem is, in Sales order there may be one or more line items with different specification & quantitys of similar project structure. Now what I need is for each line item in sales order system should create project structure useing assembly processing.

Is this possible? if yes what settings are required?

Thanks & Regards,

Tushar Patil

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

In any case, only one project will be created for one SO via Assembly processing. SD-PS indicator will ensure different roots in same project. For eg in case of 'n' line items in SO, project with 'n' root level (1st level) elements will get created.

If you wish to use SD-PS indicator, ensure that your project profile allows multiple roots. In OPSA, 'Only one root' must not be ticked.

Regards

Former Member
0 Kudos

Hi

go thru following links

http://help.sap.com/saphelp_46c/helpdata/en/95/1613a8837b11d2b6700000e82d8bd1/frameset.htm

sales item wise WBS elements can be triggerred from Sales order to Project structure.U have to assign the Material no to standard WBS in CN08.

Rgds

Edited by: Shrikrishna Rasam on Aug 20, 2008 2:08 PM

former_member214674
Contributor
0 Kudos

Hi,

Yes it is possible...check cj92 in "control data" there is a a check box SD/PS assignment.