Dear SAPIENTS,
I would like to know the details description of QM control key in material master.
I have defined control key 0007 in which Release required, Invoice block is selected. Now at the time creating Po for this material following error is coming Control Key can not be used here
Can anybody tell me what is reason behind it?
Regards,
Kaushal Rai
Hi,
For this control key setup you need to Maintain Quality Info record.
Go to QI01 -> enter Material code and Vendor code and process the Info record, then create PO.
Let me know if any error.
Regards,
S.Babusingh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Shyamal Babu,
QI Info record created than also same error is coming in PO. There are some other items in PO for them there is no such error. I hope this time error may not be due to QI info record created after PO?
Regards,
Kaushal Rai
Edited by: Kaushal Rai on Aug 20, 2008 12:30 PM
Edited by: Kaushal Rai on Aug 20, 2008 12:31 PM
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.