on 08-20-2008 4:36 AM
In Classic Scenario SRM 5.0 with ECC 6.0, how can I create an ECC Contract with a requirement from the Purchaser's Worklist ? Do I use the Global Outline Agreement? If so, what are the config steps ? Full points assured. Thx.
Raja
Hi Raja,
depending on the business you are able to create a
Global Outline Agreement
Follow the steps mentioned in the Strategic Sourcing Guide
at page 62
Backend Contract
Follow the steps mentioned in the Strategic Sourcing Guide
at page 70 using BADI BBP_DETERMINE_LOGSYS.
Cheers,
Claudia
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi You can create a GOA in SRM and distribute a contracts in Backend .
Basic configuration
(1) Define a transaction type GCTR
(2) No range internally in EBP and Externally in R/3,
(3) Idoc settings sending to r/3 like BLAORD, COND_A
(4) You must have a role to create a GOA as SAP_BBP_STAL_STRAT_PUR-
CHASER.
(5) You may need to map all condition type in SRM and R/3.
(6) Refer this notes 646903 - Global outline agreement: Tips and tricks
You can refer some related links...
http://help.sap.com/saphelp_srm50/helpdata/en/42/f93dfd975f3ee6e10000000a1553f7/frameset.htm
http://help.sap.com/saphelp_srm30/helpdata/en/7d/0a093f7c392e5ae10000000a114084/content.htm
regards
Muthu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.