cancel
Showing results for 
Search instead for 
Did you mean: 

Requirement Group In MD04

former_member677849
Participant
0 Kudos

Hi,

Please guide me for requirement group in MD04. Where its setting done and what condition they are group.

I have rememmber setting done MRP veiw-4 , But grouping not take place , Please help me Where wrong doing ?

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member677849
Participant
0 Kudos

ok

Former Member
0 Kudos

Dear Rajesh,

Go to material master and select MRP3 view. There see what is maintained for "Strategy group". Now go to OVZG, select this Requirement Class and tick the field "Rq" against this.

Now go to OVZH, select your Requirement Type and ensure that the above Requirement Class is assigned to your Requirement Type.

Regards

Amjath

srinivasa_maruvada
Active Contributor
0 Kudos

Hi Rajesh

Check at SPRO-Controlling-Product Cost Controlling-Cost object controlling-Product ocst by sale order-Control of Sales-Order-Related Production/Product Cost by Sales Order

Check here all options

Thanks

Srinivas